The Concept

The five floor podium building with its organic structure encompasses the 87 m (285 ft) high office tower and the foyer. The foyer is located in the inner courtyard and adjoins building unit A (high rise) and B (podium) in the north and the building units D and E (podium) in the south; connection level is the roof over the 2nd floor. This foyer will be used for events and is the location of the ADAC Event World among other things.

 

In total 1,152 façade units with an area of 10,000 sqm (107,600 sq ft) cover the 18th floor office tower and 2,674 façade units with an area of 9,000 sqm (96,900 sq ft) the podium building. The horizontal and vertical closed off envelope of the foyer includes a roof area 2,300 sqm (24,750 sq ft) and a façade area of 880 sqm (9,500 sq ft).

Gallery
0104
The Project
Scope of Work

10,000 sqm (107,600 sq ft) double skin façade, 9,000 sqm (96,900 sq ft) window construction, 2,300 sqm (24,750 sq ft) steel roofing and 880 sqm (9,500 sq ft) steel walling.

Technical Details

OWNER: Allgemeiner Deutscher Automobil Club e. V.

CLIENT: ARGE Neubau ADAC Zentrale

ARCHITECT: sauerbruch hutton

SITE MANAGEMENT: Ed. Züblin AG Direktion Zentrale Technik

More Information